East McEwen Drive Roundabout Improvements

Print
Press Enter to show all options, press Tab go to next option

Photo of project limits 

Click here to view larger image

Description

The City of Franklin is utilizing City funds to improve the roundabout at the intersection of East McEwen Drive and Cool Springs Boulevard/Oxford Glen Drive.  The final project will include: a right-turn bypass lane from westbound East McEwen Drive onto northbound Cool Springs Boulevard, a right-turn bypass lane from eastbound East McEwen Drive onto southbound Oxford Glen Drive, reconstructed intersection approaches to reduce speed, and updated intersection lighting.

Location

Intersection of East McEwen Drive and Cool Springs Boulevard/Oxford Glen Drive

Contact

David Hodnett, P.E.
Staff Engineer 2
615.791.3218
david.hodnett@franklintn.gov

Schedule

DESIGN:  Complete!
ROW:  March 2019*
CONSTRUCTION:  Bid – March 11, 2019, Start – May 2019*, End – December 2019*
(*Denotes Estimate)

Project Documents

Final Construction Plans (Rev. 2-18-19)